New Build

The slab is down and core filling almost complete

Progress Update Six
We’re into week seven of our brand spankin’ new 220+m2 build and this week was an incredibly important milestone for us and builder Luke. Without a hitch, the concrete slab was given the tick of approval by our engineers and our trades have kept on progressing with core filling the retaining walls and cleaning up the site with a small bobcat.

New Build

Up up up and away with the retaining block wall

Progress Update Four
We’re into our fourth week of the project and running to schedule. We currently have the team of block layers onsite errecting huge retaining walls to sound proof our kennel room and to assist hold up the second storey. Very exciting!

New Build

Digging out the all important Hospital footings

Progress Update Three
We’ve had semi trailers, utes, excavation equipment and workmen galore this week ensuring our footings are ready for concrete. It’s been an exciting process watching the earthworks unfold – bringing us one step closer to our opening date in March 2016.

New Build

Earth Works Commence at Windaroo Vet

Progress Update Two
We’ve had the local crew from MegaEarth here for the past two weeks working day and night (ok maybe not night) shaping, digging and moving over 3,000m3 from our premises.

New Build

Windaroo Vet is moving to Bahrs Scrub

Progress Update One
Welcome to the Windaroo Vet Surgery blog, where we will be sharing our latest and greatest project – our bran spankin’ new purpose built premises just down the road at Bahrs Scrub.